- Keeping a data center powered on backup can still remove its load from the grid. A setting that avoids unnecessary transfers still needs to trigger transfer on faults. Our synthetic UPS simulation tests both goals before accepting a counting configuration.
- In a run using cached model replies, an added simulated fault defeated the preliminary candidate: its voltage dips were more than 90 seconds apart and stayed above the deep-sag trigger. The proposed test exposed a gap in both transfer paths.
- The second pass rejected all 32 candidates and returned no configuration. Require a recommendation to survive added tests, with withdrawal when none passes. https://veriprajna.com/demos/data-center-grid-interaction #DataCenters #PowerSystems #GridReliability